Latest News

| 2017 | 2016 | 2015 | 2014 | 2013 | 2012 | 2011 | 2010 | 2009 | 2008 | 2007 | 2006 |

 

For further information please contact our Media Relations:

Camarco
107 Cheapside
London
EC2V 6DN

Tel: +44 (0) 20 3757 4980

Released 07:00 5-August-2015
Number 1099V

Stratex International Plc / Index: AIM / Epic: STI / Sector: Mining

 

Stratex International Plc

('Stratex' or 'the Company')

Altintepe Gold Mine Cold Commissioning to Commence mid-August

 

Stratex International Plc, the AIM-quoted exploration and development company, is pleased to provide a progress update on mine construction at its 45%-owned Altintepe Gold Project (‘Altintepe’ or the ‘Project’), where joint-venture partner Bahar Madencilik (‘Bahar’) has been funding all pre-production costs, including US$39 million towards construction. Construction is on track for completion in August 2015, and pre-operational testing (‘cold commissioning’) will commence from mid-August ahead of hot commissioning and ultimately full-scale production.  

 

Bob Foster, Stratex Chief Executive, said: “Our partners continue to make good progress and advise that construction is still due to be completed this month, with first gold pour expected in the following few weeks. The professional approach to all aspects of the construction is a credit to their commitment to delivering Turkey’s next producing gold mine.”

 

Further details: 

Since Stratex’s last construction update (announcement dated 25th June 2015), Bahar have advised the Company of the following key developments:

· Installation of low permeability soil liner fill and geomembrane 50% complete - installation of pipework and diversion channels progressing well;

· Dry commissioning of ADR plant underway;

· Mechanical and electrical installations of crusher and screening sections complete - conveyor and punch list item works are underway;

· Construction of gold room and installation of internal mechanical works completed – internal electrical works nearing completion;

· Mechanical installation of agglomerator complete – overland conveyors installation and electrical and automation works are in progress; and

· Cold commissioning of grasshopper system to commence mid-August, ahead of leach pad and crusher testing once construction is completed.

 

Bahar advise that construction remains on track to be completed in late August 2015 and they remain confident that first gold production will be achieved by the end of Q3 2015, subject to weather conditions and provided that there are no unforeseen circumstances. In the meantime the court’s decision on  legal challenges relating to the project’s original Environmental Impact Assessment is awaited (please see press releases dated 23rd February 2015 and 5th May 2015).

 

For more information and recent photos of the mine development at Altıntepe, please click the following link http://www.stratexinternational.com/project/Altıntepe.  

 

 

* * ENDS * *

 

For further information please visit www.stratexinternational.com, email [email protected], or contact:

 

Stratex International Plc

Tel: +44 (0)20 7830 9650

Bob Foster / Christopher Hall / Claire Bay

 

Grant Thornton UK LLP

Tel: +44 (0)20 7383 5100

Philip Secrett / Melanie Frean / Jen Clarke

 

Northland Capital Partners Limited

Tel: +44 (0)20 7382 1100

Gerry Beaney / David Hignell

Abigail Wayne /John Howes (Broking)

 

Yellow Jersey PR Limited

 Tel: +44 (0)7768 534641

Philip Ranger

           

 

Notes to Editors: 

Focused on the exploration and development of gold and high-value base metals, Stratex International is active in Turkey and Senegal and has strategic interests in East Africa and Ghana. Since listing on AIM in 2006, Stratex has had an impressive track record of successful exploration supported by joint-venture partnerships, both with major international mining companies and local companies to maximise the potential of its discoveries.

To date Stratex has discovered more than 2.2 million ounces of gold and 7.09 million ounces of silver, as well as 186,000 tonnes of copper. The Company is looking to completion of construction of its 45%-owned Altıntepe gold project in Turkey in August 2015 and anticipates gold production before year-end. Additionally a 1% production royalty capped at US$20 million will be due from the Öksüt project, also in Turkey, with first production provisionally targeted for Q2-2017 by owners Centerra Gold. With its current cash position and projected cash returns, the Company is well-placed to advance its existing exploration programmes and is also actively seeking to acquire advanced projects that are at the drill-ready stage or even have identified resources.

 

Altintepe mine sale sees Stratex International post interim profit

Marcus Engelbrech, chief executive of Stratex International plc ( LON:STI ) discusses with Pro...

Stratex International results chart a period of transformation for the gold exploration group

There has been significant activity across the reporting period with the sale of our Altıntepe inves...

Stratex agrees sale of Brazil iron ore mine

The consideration will be paid over a 17-month period

Stratex aligns previous Crusader agreements with new merged entity

As the Scheme of Arrangement falls into place, Stratex is aligning old Crusader arrangements with th...

Crusader updates resource estimates of Brazil project as part of merger with Stratex

Stratex International has proposed a reverse takeover of Crusader Resources



designed and produced by fresh01.com